Asanko’s Nkran gold mine achieves 100% reconciliation through blast movement monitoring

Asanko’s Nkran gold mine

Commodity Ore Grade Geology Powder Factor Flitches Location
Gold High* Structured 0.6 kg/m3 2  Africa

Asanko Gold’s Nkran mine, located in Ghana, is an open pit operation in the Kumasi Basin.

  • Mineralisation is shear-hosted in a sedimentary basin with Granitic intrusions
  • Blasts are fired in six-metre (20 ft) benches and mined in two flitches (3 m)
  • A proven reserve of 4.4 Mt at 1.85 g/t gold, the site contains high grade ores (up to 2.0 g/t)

Challenges

Ore loss and dilution negatively impacted mill feed ore grade and ounces
  • Ounces produced vs reserve model reconciliation was 18% below target
  • Mill feed ore grade was 10% below reserve model expectation
  • Blast movement, causing ore loss and dilution, was considered to be contributing factor

 

Solution

The BMM System accurately measured blast movement and translated post-blast dig lines
  • Blast movement monitors (BMMs) were installed in monitoring holes throughout the shot
  • Installation and detection as per site standard operating procedures
  • BMM System calculated new dig lines for each flitch, and areas of ore loss and dilution that would have occurred without monitoring

 

Results

100% reconciliation for ore grade and ounces produced

By accurately accounting for ore movement in production blasts, Nkran mine has achieved significant reserve model reconciliation improvements:

  • Mill feed ore grade reconciliation variance of 102% (vs 88% over the previous period)1
  • Ounces produced variance of 100% (vs 96%)

Following is an example blast from Nkran that quantifies blast movement and additional value.

  • Measured horizontal blast movement ranged from 1.5 to 11.6 m (5 to 38 ft) and vertical movement was up to 9.8 m (32 ft)

In this blast, the mine site added US$237,000 of value.

  • Maximized ore yield—recovered 2,8002 tonnes of additional ore at a value of US$137,0003
  • Reduced dilution—diverted 5,500 tonnes of waste from the mill, avoiding US$100,0004 of milling costs

* Average grade of ore polygons
1. www.asanko.com
2. Numbers are rounded
3. Calculated at a gold price of US$1,250/oz
4. Based on milling costs of $18 per tonne

Accounting for blast movement added US$237,000 of value—in one blast

 

Asanko’s Nkran gold mine

BMT